Hi All,
I need your advise before enabling Chores --> Single/Multiple Commit.
My understanding about Single/Multiple Commit is , if a chore has 3 TI's which need to be executed in a sequence. When the chore is executed, after completion of all the TI jobs commit is done instead if I opt for Multiple Commit , commit will be done after the completion individual TI process.
Scenario
Chore
TI Process 1
Sub TI Process 1
Sub TI Process 2
TI Process 2
TI Process 3
In the above case how does Multiple commit work for Sub TI process
Thanks,
Radhika